Fire Station Two
The Capital Bond Program includes the construction of a new fire station to replace Fire Station Two located on W. Hill Street in the Oakhurst neighborhood.
Budget: $1,600,000
 |
|
(Click to enlarge)
|
Status: Ready for Bid
Bid Date: June 11, 2008
Construction: August 2008–August 2009
LP3 Architects
LEED Certified
4 contractors pre-qualified
 |
 |
 |
| Site Plan |
Floor Plan - Level 1 |
Floor Plan - Level 2 |
Construction to Start on Decatur Fire Station No. 2 in Oakhurst Village
The City Commission has awarded a contract for the construction of Fire Station No. 2 to the low bidder, Ward General Contractors of Kennesaw, in the amount of $1,434,000. The new fire station is located at 356 West Hill Street in Oakhurst Village.
Construction of the new fire station is being funded by the City’s capital bond program. LP3 Architects of Decatur designed the building, which is expected to be the City of Decatur’s first LEED certified building. Construction is expected to begin during the week of July 21, 2008 and to last about 10 months.
|
 |